Baseline Assignment Work Timephased and Assignment Work Timesphased in same chart RRS feed

  • Question

  • HI, how do I get Baseline Assignment Work Timephased and Assignment Work Timephased in same chart if when I try linking the 2 tables together in the data model it can't achieve it due to a many to many relationship?  I am using OData into Excel.

    Thanks in advance.

    Dan

    Monday, June 26, 2017 11:38 AM

Answers

  • In PowerQuery, bring in the Projects table too.  Then define the relationship between the project IDs.  

    then you can plot in Excel


    Ben Howard [MVP] | web | blog | book

    • Marked as answer by Dan Kient Monday, June 26, 2017 1:54 PM
    Monday, June 26, 2017 12:19 PM