none
changing Project calendar RRS feed

  • Question

  • Hi,

     

    how can I change the project calendar thru MS Project 2010 (with SP1) which is linked to the PWA (it suppose to read the calendar from the PWA but it has new calendar named "Calendar1" which I dont recogbise.

    I receive an error massege "the project calendar is not available- please change it" but I cant find where to change. thru the Project information - I cannot choose the calendar name which I have in the PWA.

     

    Thanks,

    Hanni


    Hanni, PMO
    Monday, December 12, 2011 6:33 PM

Answers

  • Hanni --

    When you launched Microsoft Project 2010, did you connect to Project Server? You will know you are connected to Project Server by looking in the lower left corner of your Microsoft Project application window.  You should see a globe in the lower left corner, and if you float your mouse pointer over the globe, the system will display a tooltip indicating you are connected.  Let us know and we will try to help.


    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    Tuesday, December 13, 2011 1:07 PM
    Moderator

All replies

  • Hanni --

    You change the Project Calendar in the Project Information dialog.  Did your Project Server administrator actually create the custom calendar that you want to set as the Project Calendar?  If you try to select a calendar, what error message do you see if you try to change it in the Project Information dialog?  Let us know and we will try to help.


    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    Monday, December 12, 2011 11:40 PM
    Moderator
  • Hi,

     

    When I try to change the project calendar thru the project information dialog - it doesn't give me the PWA calendar as one of the options (I have calendar1, calendar2 etc. as the calendar options - none of them is a familiar calendar. I have only one activated calendar - the system default - which named simply "calendar". no 1 , 2 or any other number as suffix.

     

    Thanks,

    Hanni


    Hanni, PMO
    Tuesday, December 13, 2011 7:32 AM
  • Hanni --

    When you launched Microsoft Project 2010, did you connect to Project Server? You will know you are connected to Project Server by looking in the lower left corner of your Microsoft Project application window.  You should see a globe in the lower left corner, and if you float your mouse pointer over the globe, the system will display a tooltip indicating you are connected.  Let us know and we will try to help.


    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    Tuesday, December 13, 2011 1:07 PM