field [Minutes Per day] in the Formula editor of PWA RRS feed

  • Question

  • Hi,

    Where can we find , in the Formula editor of PWA, the field [Minutes Per day] ?

     Thanks

    Sunday, April 16, 2017 3:46 PM

Answers

  • Robert6156 --

    I just did a quick check, and it appears that the Minutes Per Day field is not listed in the Fields pick list in PWA.  For that reason, I would recommend that you create your formula using the Microsoft Project Professional user interface and then copy the formula to a new field in PWA.  Using Microsoft Project, you can find the Minutes Per Day field by clicking Field > Project > Number.  Hope this helps.


    Dale A. Howard [MVP]

    • Marked as answer by Robert6156 Saturday, April 22, 2017 4:51 PM
    Sunday, April 16, 2017 6:47 PM