    How does one filter out completed tasks in the Projects 2010 Team Planner?

    With best regards,

    Thursday, August 18, 2011 10:36 AM

Answers

  • Since the view is from the resource side you can not filter out completed tasks.  However, you can apply a grouping that will group the completed tasks separate from the uncompleted tasks.

    When in the Team Planner view select View -->  Group --> Completed and Incomplete Resources.

    The completed tasks are moved to the bottom and the incomplete will stay at the top for each resource.


    Ellen Lehnert, PMP, MCT Training/Consulting/Author ellen@lehnertcs.com, www.lehnertcs.com Author "Managing Projects using MS Project 2010 desktop" courseware, www.MVP-Press.com
    Thursday, August 18, 2011 12:55 PM
    Moderator

All replies

  • Since the view is from the resource side you can not filter out completed tasks.  However, you can apply a grouping that will group the completed tasks separate from the uncompleted tasks.

    When in the Team Planner view select View -->  Group --> Completed and Incomplete Resources.

    The completed tasks are moved to the bottom and the incomplete will stay at the top for each resource.


    Ellen Lehnert, PMP, MCT Training/Consulting/Author ellen@lehnertcs.com, www.lehnertcs.com Author "Managing Projects using MS Project 2010 desktop" courseware, www.MVP-Press.com
    Thursday, August 18, 2011 12:55 PM
    Moderator
  • You can also update the look of Actual Work (completed tasks use this style). I've set the border, text, and fill to light gray before so that way the completed tasks fade into the background more.

    You can set the look of Actual Work on the Team Planner's format tab. To update the text you need to go through Text Styles also on the Format tab.

    Thanks,

    Heather

    Friday, August 19, 2011 1:07 AM
    Moderator
  • This solution will group the percentage of all tasks per resource and will not filter the uncomplete task ! 

    why we cannot just have a filter that remove complete tasks from team planner view ?

    Monday, May 11, 2015 8:11 AM
  • Hi,

    I created a filter NoRemainingWork and applied to Team Planner. Could this fit to your requirement?

    Regards
    Barbara


    To increase the value of this forum, please mark the replies that helped to solve your issue as answer. If you find answers to questions from other forum participants to be helpful, please mark them as helpful. Your participation will help others to find an appropriate solution faster. Thanks for your support!

    Monday, May 11, 2015 8:24 AM
    Moderator