  • hi team

    i have created an exception on resource calender but they don't seem to reflect on resource allocation

    Resource allocation

    is there a synch jib or something ?

    how can i synch them


    tanveer


    Wednesday, September 13, 2017 6:05 PM

Answers

  • The Tanveer,

    The view is showing correctly, as the capacity for the period.  The allocation could be for several reasons...

    1. The project has not been opened in MS Project and republished.

    2. The tasks relating to the assignment are manually scheduled.

    3. The tasks are autoscheduled, but the checkbox "scheduling ignores resource calendars" is selected.  


    Ben Howard [MVP] | web | blog | book

    • Marked as answer by tanveer.attar Thursday, September 14, 2017 6:12 AM