microsoft project server 2007 Individual rights don't work but the Category permissions do? RRS feed

  • Question

  • I want to give a User rights to handle Timesheets but they're not part of the Resource Managers group. When I add them to the Resource managers group they can perform the operations, but when I take them out of the Group(since they dont actually belong) and give them individual rights it doesnt work. Any thoughts? thanks in advance
    Friday, January 21, 2011 5:17 AM

Answers

  • Hi msp admin,

    You need to set the appropriate permission to handle Timesheets of the Group those users belongs to.

    Dont add them to the Resource Managers Group, go to the  group (Project Managers, Team leads, etc.) those users belongs to.

    • expand the global permission of the group,
    • and set the permission 'Allow' related to the timesheet as per your requirement.

    Does this help?


    | Khurram Jamshed | Follow my blog about Enterprise Project Management Solution | http://khurramjamshed.blogspot.com |