locked
Lags RRS feed

  • Question

  • Is it possible to use multiple lags between two activities?
    Thursday, May 24, 2012 6:23 PM

Answers

  • You can only have a single dependency between two activities.  The choices are Finish to Finish, Finish to Start, Start to Start and Start to Finish; and each can contain a lag time (which can be expressed as a number of days or a % of the predecessor duration, either as a +ve or - ve value).  

    So, it's a long answer which leads to a "No".



    Ben Howard [MVP] blog | web

    Thursday, May 24, 2012 7:26 PM