Task Updates - Schedule Warning RRS feed

  • Question

  • Hi,

    When trying to edit a task in the schedule view in project webapp this message shows up. I'm just trying to marked it complete and I'm the resource on this projects and assigned to the task.

    What setting is causing this error?

    "We cannot make that change because Project Web App is set to only allow actual work to be entered by team members through Timesheets or My Work."

    Thank you/Henrik

    Wednesday, March 21, 2018 1:27 PM

Answers

  • Hi Henrik,

    This is because you administrator has activated the setting to force actuals to come from the timesheet/task update.

    So you cannot directly set a %complete or work complete on a task since it must come the the approved task update or timesheets.

    Either you go through this workflow or you deactivate the setting.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller

    Wednesday, March 21, 2018 1:41 PM
    Moderator

All replies

  • Hi Henrik,

    This is because you administrator has activated the setting to force actuals to come from the timesheet/task update.

    So you cannot directly set a %complete or work complete on a task since it must come the the approved task update or timesheets.

    Either you go through this workflow or you deactivate the setting.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller

    Wednesday, March 21, 2018 1:41 PM
    Moderator
  • Perfect!!

    Thanks.

    Wednesday, March 21, 2018 5:33 PM