Viewing all project tasks in synced sharepoint list RRS feed

  • Question

  • So I know that Sharepoint can't handle the task hierarchy from MS Project, but I was wondering if there is any way to run workflows on a list created from an MS Project sync so that I can send out notifications to users when they have a task assigned or create views that would show all tasks assigned to a certain person.

    Is this possible?

    Friday, February 8, 2013 8:04 PM

All replies

  • Hello djherring,

    Yes, you can have workflows in a SharePoint List synchronized to a Project file in Project Pro. I would advise to bulid and test the workflow before synchronization and have one thing in mind: Most of the time you will create tasks during the workflow. Make sure the task list you are using is not the same list of your project plan because by default it will be.

    Best regards,


    Rene Alvarez