Scheduling Problem in Project server 2010 RRS feed

  • Question

  • Hi ,

    Can Any one Help me,

    I have a calender with 7am to 3pm as work timings with no break as 8 hours working per day, and in the month of August 2nd week the work hours is 8Am to 2PM.

    Now When i try to create a task in AUG 2nd week the Task is taking 8 hours for 1day not 6 hours and schedule is going to next working day,

    EX:if  i give  duration 1 day then its taking --> start date time (4-Aug-14 8am) finish date time is  (5-Aug-14 10Am) ----> ie. 6hours in 4-aug & 2 Hours in 5 Aug.

    How can i solve this issue, How to make the Task to End on same day and it should take 6 hours a day.

    How to make the 8 hours tasks and 6 hours task to show duration 1 day in the same project.

    Thanks In advance.



    Kumar KSV



    • Edited by kumar ksv Tuesday, August 19, 2014 5:59 PM
    Monday, August 18, 2014 5:23 PM

All replies

  • Have you tried setting your view to task view and then assign 6H for the  days that require six hours

    Cheers!


    Michael Wharton, MVP, MBA, PMP, MCT, MCTS, MCSD, MCSE+I, MCDBA
    Website http://www.WhartonComputer.com
    Blog http://MyProjectExpert.com contains my field notes and SQL queries

    • Marked as answer by kumar ksv Thursday, September 4, 2014 7:49 AM