Is it possible to reschedule of each task depend on total term automatically? RRS feed

  • Question

  • Hi,

    if I have WBS(Project A) which its total term is 10 months.

    And I want to use same WBS(Project A), however I want to change total term from 10 months to 9 months.

    Then, is there any way that each task's duration can be changed according to new term(9 months)?

    In other word, there is no task name change, but every each task's duration need to be changed automatically.

    Novice


    • Edited by 초보자2 Monday, November 13, 2017 9:30 AM
    Monday, November 13, 2017 2:27 AM

All replies

  • Hello, just shorten the duration of a task on the critical path. In order to display the critical path, go to the ribbon „Format“ and select the respective checkbox.


    Best regards,

    Julian, PMP, MCP, MCSA, MCSE

    Blog: https://project-brain.com

    Note: Posts are provided “AS IS” without warranty of any kind, either expressed or implied, including but not limited to the implied warranties of merchantability and/or fitness for a particular purpose.


    Monday, November 13, 2017 7:06 AM
  • Thank you for your response.

    My WBS has my task, so I am interested in automatic change rather than manual above all.

    If there is no automatic way, I will try to change like your proposal.

    BR,

    Novice