Project Online - Analyze Resoureces tab is gone RRS feed

  • Question

  • Hi

    I have started using project online and so far it is a little hard to find how to use it. One thing that is a little strange is that I saw in a demo video on MS product website that there should be a Analyze Resources tab to the right of the Analyze Cost tab.

    In my view the tab is gone, is it settings or? 


    Wednesday, September 11, 2013 9:26 AM

Answers

  • You will only see the "Analyze Resources" Tab, if you check the "Analyze time-phased project resource requirements against organizational resource capacity" check box on the Define Properties page. This is not specific to Project Online. Applies to on-premises as well.

    Prasanna Adavi,PMP,MCTS,MCITP,MCT http://thinkepm.blogspot.com

    • Marked as answer by StenholtMygind Wednesday, September 11, 2013 10:24 AM
    Wednesday, September 11, 2013 9:53 AM