DPM 2007 Backup Jobs RRS feed

  • Question

  • Hi Guys,

     

    Just a quick question is it possible to re-run a month end or any backup job that the Alert has been inactivated after failure?

    thank you in advance

    Thursday, December 1, 2011 9:35 AM

Answers

  • Hi Mat,

    In an inactive alert you don't have the option to "re-run" the operations since it's stated in the alert "no action is required becauase this alert is inactive". You have the option to veiw your inactive alerts by checking the checkbox in monitoring / alerts.

    If you want to create a recoery point you have the option the create one manually, though you don't have to option to set a date of when the recovery point should be created from. You can only create a recovery point manually from the latest data.


    Best Regards

    Robert Hedblom

    MVP DPM


    Check out my DPM blog @ http://robertanddpm.blogspot.com

    Thursday, December 1, 2011 10:18 AM