My PM is on holiday; but I want to assign them a project and make them the status manager for all tasks RRS feed

  • Question

  • Is this possible.

    I can create a project and become the Status Manager of the tasks: but I want to hand it off to a PM who is on holiday. How do I assign them Status Management over all tasks?

    Andrew


    Trying to stop the swap to Salesforce - but the errors keep a coming

    Tuesday, June 25, 2013 12:38 PM

Answers

  • Andrew --

    It is not possible to designate someone else as the Status Manager for all tasks in a project.  In Project Server, the other PM must open the project and set him/herself as the Status Manager.  Because this is how the software works, you will need to wait until the PM returns from holiday before the problem can be solved.  Hope this helps.


    Dale A. Howard [MVP]

    Tuesday, June 25, 2013 4:43 PM