Task Approval before Publishing RRS feed

  • Question

  • Hello,

    I have received a requirement to customize our Project Server 2013 implementation as follows:

    * Several project managers can add tasks to the same project plan

    * A centralized focal point is  responsible of auditing and validating added tasks

    * When a project manager adds new tasks, the focal point gets notified by email.

    * The focal point has to approve or reject the added tasks. If he / she approves them, the tasks are published. If he / she rejects them, the tasks are removed from the plan.

    Are there any recommendations on the best way to implement these requirements? I have looked into Project Server workflow but they does not seem to support such requirements.

    Thanks in advance.

    Monday, April 9, 2018 6:25 AM

All replies

  • Moezz --

    Rather than trying to automate this, I would recommend that it be a simple process that the PMs have to follow before publishing the project.  It would rely on good old human communication, rather than trying to automate it through the software.  Just a thought.  Hope this helps.


    Dale A. Howard [MVP]

    Monday, April 9, 2018 6:23 PM
    Moderator
  • Hi Dale. Personally, I agree with what you said. However, our company is facing human challenges getting that to work. For that reason, I was asked to find a way to automate the process.
    Tuesday, April 10, 2018 5:36 AM