why doesn't task linked to other task on Gantt not show up on Timeline? RRS feed

  • Question

  • I'm complete newbie.  This screenshot shows my Gannt chart with a task I linked to a (previous task) I want to understand Project in this case where I can't do study for one thing until I finish design for something else. I'm pretty sure I saw all three tasks on the Timeline before I linked one to another?  What am I missing in my understanding of Gantt chart vs Timeline view?  Thank you.
    Saturday, June 4, 2011 7:33 PM

Answers

  • Hi,

    Linking taks does not affect appearance on the timeline, sorry. Select the task and click the button "add to timeline" on the task ribbon to make it appear.

    Greetings,

    • Marked as answer by hazz Saturday, June 4, 2011 9:42 PM
    Saturday, June 4, 2011 8:20 PM
    Moderator

All replies

  • Hi,

    Linking taks does not affect appearance on the timeline, sorry. Select the task and click the button "add to timeline" on the task ribbon to make it appear.

    Greetings,

    • Marked as answer by hazz Saturday, June 4, 2011 9:42 PM
    Saturday, June 4, 2011 8:20 PM
    Moderator
  • thank you!  that was easy! there it is!