none
Hours entered by delegate in time sheet not reflecting in reports RRS feed

  • Question

  • This is for Project Server 2013. Even I have faced this issues in PS 2010 and it still continues.

    There are 2 users. user A and user B. User A is on leave and User B has been set up as a delegate to fill out time sheets for user A. User B logs in and acts a a delegate for user A. He fills up A's timesheet and submits. Project manager receives task updates for A and approves. Project plan is published. But hours for user A are not reflecting is Time sheet reports.

     


    Abhijeet, MCTS | abhijeetm@outlook.com

    Thursday, February 6, 2014 11:09 AM

All replies

  • Hi Abhijeet,

    Can't say here about delegation, but yes I have faced one issue where timesheet data was not getting synch with Reporting DB.

    So to fix this please follow steps.

    1) Recall the problematic timesheet.

    2) Do some minor change.

    3) Then revert those changes.

    4)Then first click on "Save"

    5) And at last "Submit" the timesheet.

    Don't know exactly what was the reason for particular timesheets, "Reporting Timesheet Save" job was not getting fired whenever user is submitting the timesheet.

    Using above mentioned steps helped to get my timesheet data get synch with Reporting DB.

    Hope it will work for you as well.

    Thanks !!!!


    Sachin Vashishth MCTS