  • Hi All,

    How to change the Date format in Project Server 2013 so that it should effect for all the projects.

    Firstly I have tried it Changing in MSP 2013 but it didn't effected on server.

    Please help me on this. Thanks in Advance!!


    Soumya T | EPM Consultant

    Monday, June 23, 2014 2:36 PM

All replies

  • Assuming you want to change the display format of the dates. The date formats on the Server are not controlled by MSP settings. They are controlled by the regional settings.

    To change the date format, navigate to the Gear icon >> Site Settings >> Regional Settings, and change the "Locale" to the region applicable to you.


    Prasanna Adavi,PMP,MCTS,MCITP,MCT TWitter: @prasannaadavi Blog: http://www.prasannaadavi.com

    Monday, June 23, 2014 2:56 PM