    I have two phased project (master project). Ms project displays % completed from both phases, but I need to display % completed only from first phase. How can i do it?

    Tuesday, July 17, 2012 6:27 AM

Answers

  • Denis F --
     
    If you insert the % Complete column in your master project, and then collapse each of the subprojects, then you can see the % Complete for each subproject.  At the master project level, however, there is no way to force the software to calculate the % Complete value for only one of the subprojects.  In other words, the answer to your question is no, this is not possible.  Hope this helps.
     

    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    Tuesday, July 17, 2012 12:36 PM