MDT 2013u2 - new task sequences? RRS feed

  • Question

  • If I upgrade from 2013 update 1 (original version) to update 2 will I have to recreate all my task sequences?

    Additionally will Update 2 work with ADK 10.0.26624?

    Monday, February 29, 2016 2:46 PM

All replies

  • hi

    No you do not have to recreate your task sequences - but any changes in the task sequence template will not be implemented before you create a new task sequence.

    You MDT update 2 will work with ADK RTM and 1511 version.