Project Server 2010 and Exchange Server 2010 - Sync problem RRS feed

  • Question

  • Hello, I have two problems.

    I have configuration the synchronisation between Project Server 2010 and MS Exchange Server 2010 SP1. The people in projects get the tasks in their task list in exchange. But not in the main task list, a new task list with the name of the Project is great. Is this normal? In the video (http://technet.microsoft.com/en-us/library/ff468700.aspx) can you see at the end, that the tasks of a project, are in the main tasks list. We habe the problem, that all tasks must be sync with Black Berry, and Black Berry sync no sub task lists.

    And now the second problem. When I changed or make a task as sucessfully or to 50%, the data whre not be sync with Project Server. I have only a unidirectional way for tasks - all new tasks and changes go from Project to Exchange but not from Exchange to Project.

    Have you a idea?

    Wednesday, February 16, 2011 5:23 PM