Create a Burndown in Project 2013 with Actual Vs Planned RRS feed

  • Question

  • Create a Burndown in Project 2013 with Actual Vs Planned

    All i wanted to know is - does,

    Actual is equivalent to Remaining Cumulative Actual work 

    Planned is equivalent to Remaining Cumulative work

    Wednesday, July 13, 2016 11:06 PM

All replies

  • From Help:

    The Remaining Cumulative Actual Work field contains the work that still needs to be completed on a task or by a resource assigned to a task.

    Remaining Cumulative Actual Work

    How Calculated    The Work field contains the total amount of time scheduled for a task. When you first create a task, the Remaining Cumulative Actual Work field is equal to the total work. When you enter percent complete, percent work complete, or actual work information for a task, Project sums this up as the cumulative actual work completed for that task. Project calculates this field as follows:

    Remaining Cumulative Actual Work = Total Work – Cumulative Actual Work.

    See this information on cumulative work


    Sunday, July 17, 2016 9:08 PM