    I need some help with a Project 2013.

    So, I have Project Server and Professional.

    Several project managers who published their projects from Project Professional to Project Server (only few, not all experienced that) when they went back a few days later the found some of the tasks percentage complete is changed. Earlier it was at 100%, but then changed to another value (it is different for different tasks).

    Has anyone experienced this? Does anyone know what need to be done to fix it?  I will appriciate any help I can get!

    Thanks in advance!!! Kate