  • Hi,

    I’ve noticed that when you open an MSP 2010 plan and a resource has submitted time updates, MSP 2010 asks you if you want to apply the updates to the plan.  When you say yes, the Approval centre opens and all works fine up until when you accept the tasks, then you don’t get the option to go back to MSP and the plan you opened.  You have to manually navigate back to MSP and reopen the plan.

    Not sure if this is a bug, setting that needs to change or just because we’re not done with timesheet config?

    Thanks,

    Jaco


    Regards, Jaco van der Riet Pioneer Foods (Pty) Ltd PMO


    • Edited by JacoRiet Thursday, June 7, 2012 12:44 PM
    Thursday, June 7, 2012 12:43 PM

Answers

  • Hi Jaco,

    this is correct behavior. when you accept task it is the same as publishing changes in project. thats why if you choose "yes" and approval center is opened, and your project in MS project is closed and you have to reopen. in scenario when you have check out project in MS Project and at the same time you will approved task, potentially lead to problems

    tomas


    • Edited by Tomáš Szarka Thursday, June 7, 2012 1:04 PM
    • Marked as answer by JacoRiet Thursday, June 7, 2012 1:06 PM
    Thursday, June 7, 2012 1:01 PM

All replies

  • Hi Jaco,

    this is correct behavior. when you accept task it is the same as publishing changes in project. thats why if you choose "yes" and approval center is opened, and your project in MS project is closed and you have to reopen. in scenario when you have check out project in MS Project and at the same time you will approved task, potentially lead to problems

    tomas


    • Edited by Tomáš Szarka Thursday, June 7, 2012 1:04 PM
    • Marked as answer by JacoRiet Thursday, June 7, 2012 1:06 PM
    Thursday, June 7, 2012 1:01 PM
  • Thank you Tomas