Earned Value Reporting RRS feed

  • Question

  • Hi everyone

    I need to create an earned value report per project in either excel or ssrs. The data needs to come from the schedule for each project- I'm connected using the odata...I cant seem to find fields that will give me trend analysis.

    For example I can find

    - status date

    - acwp

    - bcwp

    - bcws

    however I need a timephased field that will give me cumulative data..essentially I need to create/plot the EV data over a timeline for each project..

    any ideas?

    thanks

    Nikki

    Tuesday, July 19, 2016 9:49 PM

All replies

  • Hi Nikki,

    Were you able to solve this?

    Regards

    Agasthya

    Thursday, October 5, 2017 8:53 AM
  • Hi Nikki.

    BCWP is the budgeted cost of work performed = EV.

    The value of the results measured in the budgeted cost.

    https://support.office.com/en-us/article/bcwp-earned-value-or-ev-fields-e0c570ea-9c7b-4864-8a6b-920ed0f7b847

    Best Regards

    John Hansleyton | https://www.mytaskserver.com/