Finish Variance Percentage RRS feed

  • Question

  • Dear All,

    Is it possible to calculate Project "Finish Variance Percentage" in project server 2013...?

    Thanks & Regards,


    -Vinod

    Tuesday, June 7, 2016 6:05 AM

Answers

All replies

  • Hi Vinod,

    I'm sure it is quite possible, it is just a matter of identifying the formula. What you do expect of the finish variance %? Would it be the finish variance divided by the project duration?

    After you know the formula, you just have to create a project enterprise custom field, and enter the formula.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller

    Tuesday, June 7, 2016 7:24 AM
    Moderator
  • can you please share the formula for Finish variance percentage?

    Thanks,


    -Vinod

    Tuesday, June 7, 2016 7:43 AM
  • Hi Vinod,

    This is actually my point. This is not something that exists out-of-the-box and neither in the project management best practices. So if you do need it, you should have an idea of what you need/want, or you should define your need, I cannot make it out for you. 

    I could surely propose something (finish variance/duration) but I don't know if it is what you want.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller

    Tuesday, June 7, 2016 7:48 AM
    Moderator
  • Actual what i need is "Finish Variance Percentage". But my doubt is:
    Finish var % = (Finish Var/Duratioin)* 100
    or
    Finish var% = (Finish Var/BL Duration)* 100

    which one is correct?


    -Vinod

    Tuesday, June 7, 2016 9:44 AM
  • I would rather use Finish var% = (Finish Var/BL Duration)* 100.

    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller

    Tuesday, June 7, 2016 10:14 AM
    Moderator
  • Thanks...!!!!!!

    -Vinod

    Tuesday, June 7, 2016 12:18 PM