Task information on a view of PWA RRS feed

  • Question

  • Hello.I wonder if any of the kind colleagues could help me.

    I wanted to show a view of the PWA(project level) the end date of a task presente on the WBS, using the unique task description as a filter. I would be grateful if someone had a workaround,probably using a formula custom table. I hope I have been clear! :O)Best regards

    Wednesday, May 18, 2016 2:24 PM

All replies

  • Hi Jorge,

      This is not available OOB, you may need to develop a custom report altogether using SSRS or Excel services to achieve this but not in project center using regular view options.


    Regards, Syed Faizan ur Rehman, CBPM®,PRINCE2®, MCTS

    Thursday, May 26, 2016 7:25 AM