project manager is not receiving tasks updates from team members RRS feed

  • Question

  • when the team member tasks accept his team lead and then team member import timesheets to the My tasks page and send it specific tasks to project manager . project manager not receiving these tasks.
    SAM
    Tuesday, July 20, 2010 5:54 AM

Answers

  • Hi Basim,

    ask your project manager to open the project plan and insert column "Status Manager". Approval will be sent to the user listed in that column. Perhaps it is the wrong person?

    Another possiblity: check your queue if someting is listed there?

    Let us know!
    Regards
    Barbara