none
Project Server 2007 SP2: Gantt with data in OLAP but not in Published or Draft Databases RRS feed

  • Question

  • Hello:

    I have an issue with MSP_Project_Timesheet OLAP database on Project Server 2007 SP2.

    I had a Gantt created in the Draft and Published Databases. After rebuilding Project Server's Cubes, the Gantt was available in the MSP_Project_Timesheet OLAP database.

    Later on, I deleted that Gantt from the Draft and Published Databases and then rebuilt the Project Server's Cubes.

    I was shocked to find that the already deleted Gantt is still visible on the MSP_Project_Timesheet OLAP database.

    I've rebuilded Project Server's Cubes several times but the deleted Gantt data is still visible on the MSP_Project_Timesheet OLAP database.

    Is there a way to solve this problem?

    Awaiting your kind reply,

    Sebastián Armas Maturana

    Project Manager

    Friday, December 4, 2015 1:20 PM

All replies