project web access not showing all the tasks RRS feed

  • Question

  • Hi,

    We are using Project Server 2003. I have assigned few tasks to one of my resources. When I login to PWA and adjust actual work hours I don't see all of the tasks for this particular resource, but I can see all in the project plan. Am I missing anything here to not display or is there any way show it back on PWA?

    Please suggest, thank you in advance!

    Thursday, August 15, 2013 1:08 AM

All replies

  • Hi,

    Never worked on Project Server 2003, but in Project Server 2007 or onwards there in option to filter the view to just show current tasks in My Tasks View, so please check if such option/setting is also available there in Project Server 2003 as well.

    If yes then uncheck "Show Current Task" and other choices/options available there.

    Hope it may help you, Thanks !!!


    Sachin Vashishth MCTS

    Thursday, August 15, 2013 3:10 PM
  • Are you sure you don't have any filters set?
    Monday, August 19, 2013 9:18 AM
  • Hi AnnKo --

    What page in PWA are you visiting to perform the actual work adjustments?

    -- tz


    Tony Zink Vice President, EPMA Company: http://www.epmainc.com Blog: http://www.epmablog.com Training: http://www.epmainstitute.com

    Monday, August 19, 2013 5:28 PM