Master projects - accepting changes from sub-projects RRS feed

Answers

  • I would say that the dialog box is intended to be used while opening a single project and not a master project. Applied to a single project, the dialog box allows you to accept or reject an update.

    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller |

    • Marked as answer by Stev Scott42 Wednesday, May 27, 2015 2:53 PM
    Wednesday, May 27, 2015 2:23 PM
    Moderator

All replies

  • Hi Steve,

    Yes it is correct. I never tried it, but I just tested it and opening the sub projects within a master plan accepts automatically the cross project links updates.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller |

    Wednesday, May 27, 2015 1:49 PM
    Moderator
  • thanks, so the Accept changes dialog box is really just informational rather then something that can be used to block the changes from acceptance?

    Steve

    Wednesday, May 27, 2015 2:17 PM
  • I would say that the dialog box is intended to be used while opening a single project and not a master project. Applied to a single project, the dialog box allows you to accept or reject an update.

    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller |

    • Marked as answer by Stev Scott42 Wednesday, May 27, 2015 2:53 PM
    Wednesday, May 27, 2015 2:23 PM
    Moderator
  • thanks Guillaume,

    Steve

    Wednesday, May 27, 2015 2:56 PM