Cost for a role and not a person... RRS feed

  • Question

  • Hi team

    In POL, I have a situation where the role is costed and not the resource (so a resource might be down graded to do fore-fill a role).  But I want the resource to complete a timesheet for the work done.  Is there a way I can have a V-lookup style enterprise field that can match the role rate against the role and still have the resource in the resource name column?

    Hope this make sense

    Many thanks 

    James 



    • Edited by JamesP435 Sunday, April 15, 2018 1:33 PM
    Sunday, April 15, 2018 1:32 PM

All replies

  • Hi James,

    This has always been an issue in Project, because you only have 5 cost rate tables per resource; if this isn't sufficient then use an alternative soln to calculate the cost based upon the hours the resource works (Excel / Power BI etc)


    Ben Howard [MVP] | web | blog | book | downloads | P2O