Resource Plan : Work unit is not valid RRS feed

  • Question

  • Hi,

    In PWA 2010 I created a Resource Plan with the timescale in weeks and workload in days. When I tried to publish it, I got the error: "Work unit is not valid".

    I set the timescale in days and the system accepted to publish the Resource Plan. 

    What are the compliant settings for the Resource Plan?

    Thanks

    Friday, April 22, 2011 10:49 AM

Answers

  • WLID,

    I tried reproducing the issue, but I was able to publish even with Timescale in weeks and workload in days. And I do not see why timescale has to effect the workload. Di you change anything else other than the timescale, for you to be able to publish?


    Prasanna Adavi, PMP, MCTS Blog: http://msprojectideas.blogspot.com
    Wednesday, April 27, 2011 2:00 PM
    Moderator