Question
-
Please can you tell me why in office project is showing more days than i enter in the Start and Finish ... I have changed the week calendar to show all working days to include Saturday and Sunday but stillWednesday, April 13, 2016 7:53 PM
Answers
-
By default, Project will compute duration based upon a 40 hour work week. You can create a custom calendar and make Saturday and Sunday working days, however, if you only setup the calendar to "show all working days to include Saturday and Sunday" then the weekend would still be counted as non-work days.
Below is a link that will show how to change the work hours/days in your calendar.
https://support.office.com/en-us/article/Change-working-days-for-the-project-calendar-323ff403-a676-428c-be11-6942bfb7210c
s/f
Jim
Jim Project
- Marked as answer by Brian Smith - MSFTMicrosoft employee Friday, April 15, 2016 8:04 PM
Wednesday, April 13, 2016 8:03 PM -
Also, below is a link describing how Project schedules tasks to build the timeline:
https://support.office.com/en-us/article/How-Project-schedules-tasks-Behind-the-scenes-df3431ab-8d8a-4047-afc6-a87b547dbac0
Thanks,
Jim
Jim Project
- Marked as answer by Brian Smith - MSFTMicrosoft employee Friday, April 15, 2016 8:04 PM
Wednesday, April 13, 2016 8:24 PM
All replies
-
By default, Project will compute duration based upon a 40 hour work week. You can create a custom calendar and make Saturday and Sunday working days, however, if you only setup the calendar to "show all working days to include Saturday and Sunday" then the weekend would still be counted as non-work days.
Below is a link that will show how to change the work hours/days in your calendar.
https://support.office.com/en-us/article/Change-working-days-for-the-project-calendar-323ff403-a676-428c-be11-6942bfb7210c
s/f
Jim
Jim Project
- Marked as answer by Brian Smith - MSFTMicrosoft employee Friday, April 15, 2016 8:04 PM
Wednesday, April 13, 2016 8:03 PM -
Also, below is a link describing how Project schedules tasks to build the timeline:
https://support.office.com/en-us/article/How-Project-schedules-tasks-Behind-the-scenes-df3431ab-8d8a-4047-afc6-a87b547dbac0
Thanks,
Jim
Jim Project
- Marked as answer by Brian Smith - MSFTMicrosoft employee Friday, April 15, 2016 8:04 PM
Wednesday, April 13, 2016 8:24 PM