none
Get the differences between summary tasks - MSProject Professional 2010

    Question

  • Hello

    Is there any option in Application.CompareProjectVersions in MsProject 2010, for get the differences between summary tasks too?. I will appreciated your help.

    Regards

    P. Aquino

     
    Wednesday, April 19, 2017 1:25 PM

All replies

  • Pedro,

    Sorry for the delay in responding.

    What exactly are you trying to do? The Compare Project Versions utility already provides differences between Project fields for summary and subtasks. The CompareProjectVersions Method simply opens the user interface. You can modify the elements shown in the report by using the CreateComparisonReport Method.

    John

    Monday, April 24, 2017 3:42 PM