Accept Timesheet and then Approve Timesheet (sequence of validation) PWA 2010 RRS feed

  • Question

  • Hello,

    I built a Timesheet approval sequence in PWA which worked fine during several weeks on a pilot:

    A Team Member fills his/her timesheet and clicks "Send Timesheet"

    A middle man in the PMO "Accepts" or reject the timesheet (We are using “Fixed approval path”)

    A Manager with the Approve permission, approve or reject the Timesheet.... but while the process is supposed to stop there, the Manager must select another user to validate his own validation: the process does not stop!

    What is wrong?

    Thanks for your help!

    PS: The Manager is his own Timesheet Manager
    • Edited by WLID1966 Monday, September 30, 2013 3:32 PM
    Monday, September 30, 2013 3:20 PM

Answers

  • Hi,

    Are you using a RBS for your resources? If yes, try to set the last "manager" (who has the Approve timesheet permission) to a upper level in this RBS.


    Gérard Ducouret [Project MVP], Certifié Project 70632, Certifié ITIL

    • Marked as answer by WLID1966 Sunday, October 6, 2013 1:54 PM
    Tuesday, October 1, 2013 6:13 AM

All replies

  • Hi,

    Are you using a RBS for your resources? If yes, try to set the last "manager" (who has the Approve timesheet permission) to a upper level in this RBS.


    Gérard Ducouret [Project MVP], Certifié Project 70632, Certifié ITIL

    • Marked as answer by WLID1966 Sunday, October 6, 2013 1:54 PM
    Tuesday, October 1, 2013 6:13 AM
  • Thanks

    That worked, but why?