How to spread the actual work until the status date ? RRS feed

All replies

  • Hi,

    On the TASK tab, you can mark the task on track, meaning it will spread the actual work until the status date, equal to the work.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller

    Tuesday, March 19, 2019 11:12 AM
    Moderator
  • eng_mohamed_atef,

    Wait a minute, actuals are what really happened. They are entered (spread) according to how they occurred, not by any action on Project's part. The only exception to this is for tasks that are level-of -effort. Actual work for those type tasks is not based on accomplishment but rather on the passage of time.

    There must be some miscommunication on what you really mean. Please clarify.

    John