none
Gantt Chart showing different progress in project center than Project Professional RRS feed

  • Question

  • Hello,

    I am fairly new to PWA environment, I have entered my projects in PWA and been updating them through Project Professional but now I am looking at the summary task progress in the Project Center and its showing progress in the future but when I open the project in Project Professional, all the progress is in the past as it should be. I can't figure out why this is happening. Any help would be appreciated. And if you need more information please let me know. 

    Thanks,

    (could not upload picture because they could not verify my account)

    Tuesday, July 9, 2019 6:47 PM

All replies