Finding out how work was done out of the total planned work RRS feed

  • Question

  • hello

    I have 3 types of resources in my project - Technician, Engineer, Manager.

    I need to find out for each resource (separately) how much work has already been done and how much is left until the end of the project.

    Saturday, January 25, 2020 7:46 PM

All replies

  • EN1986 --

    Have you created a custom resource field that identifies whether each resource is a Technician, an Engineer, or a Manager?  If so, you could apply the Resource Usage view, apply the Work table, and then apply grouping on your custom field.  Assuming you are entering task progress in your project schedule, you could study the Actual Work and Remaining Work for each group.  Just a thought.  Hope this helps.


    Dale A. Howard [MVP]

    Sunday, January 26, 2020 10:11 PM