How Do you Clear Errors RRS feed

  • Question

  • HI,

    When I viewed my status update history, the list below appeared. Does anyone know how I'm supposed to go about clearing these "internal" errors? thanks.


    Judy Washington

    Monday, March 18, 2013 6:21 PM

All replies

  • Try deleting the timesheet and then recreating.

    The errors can be caused by things like, trying to enter hours when zero hours are remaining, and entering time for tasks where the time is to far before or after the finish date.  The project manager needs to be certain to push unfinish work to the status date each week and publish projects to prevent this.

    Cheers!


    Michael Wharton, MVP, MBA, PMP, MCT, MCTS, MCSD, MCSE+I, MCDBA
    Website http://www.WhartonComputer.com
    Blog http://MyProjectExpert.com contains my field notes and SQL queries

    Thursday, April 11, 2013 3:13 AM
    Moderator
  • Thanks Michael.  I believe deleting and re-creating the timesheets are what we ended up doing. I will keep your input in mind for the future.