Resources Work view in PWA of a Master Schedule RRS feed

  • Question

  • I have a Master Schedule with 17 sub-projects published in PWA. When I go to the Resources Work view of the master schedule in PWA it shows a list of all the resources, however it is showing zero work hours for all of the resources. When I select one if the sub-projects individually from the project center the resources work view pulls correctly. Does anyone know the reason why it is not working for the master schedule? Is there a way to correct the issue? Or does a new resource view for master schedule need to be created?
    Monday, January 7, 2013 9:38 PM

All replies

  • Hi Cindy,

    this information is not aggregated in Project Detail views. Only the work of the master plan itself is shown. You will need some kind of report in Excel Services, SQL Reporting Services or some other technology that aggregates the assignment work of your 17 sub-projects.

    Hope that helps

    Kind regards

    Christoph

    Wednesday, January 9, 2013 7:34 PM