I'm not sure if anyone has experienced this issue before.
System Specs: Single Server Install Running:
Windows 2003 R2 64-bit SP2
Office Project Server 2007 Version: 12.0.0.6535
SQL Server 2008 Standard Edition (64-bit) 10.0.2531.0 SP1
The issue that I'm having is that the user who originally owned the OLAP Cube Build jobs has been deleted when the cube build fails no notification is being send out. I would like to update the owner of the Olap Cube jobs so that if the nightly cube build
job fails a notification is send out to the System Account which has been configured with a group mailing list.
I have already tried the following.
1. Reconfigure Cube Build Settings using system login.
2. If I run cube build on demand that job to build the cube is owned by the user to requested it.
Thank you in advance.