In Project Center How do you get the GANTT view to list projects by Workflow Phase RRS feed

  • Question

  • I have created projects based on the OOTB workflows but it does not list them by Workflow phase in the Project Center GANTT view.  I have seen the experts list the projects this way. 

    I am sure I am missing a simple setting

    Thanks

    Andrew

    Wednesday, October 24, 2012 4:03 PM

Answers

  • Hi Andrew,

    Use a "Group By" to adjust the list. You will need to add this to the option. 

    1. On the Quick Launch menu, select Server Settings
    2. Under Look and Feel, select Manage Views
    3. Under the Project Charter heading, select Summary
    4. Add the field Workflow Stage Name under the Table and Fields
    5. Under Format View, add the Workflow Stage Name to the Group By
    6. Click Save