  • Good morning,

    I have a task "Task A" that I have extended by 5 days.

    ie. Task A     4/9/12    to  5/7/12    was at 40% complete

    the person working on it asked me to give him until the 15 of May.

    So I extended it.

    ie. Task A     4/9/12    to  5/15/12  

    and he said he is 60% complete.

    So when I try to update it to 60% it automatically goes to 100%

    Why is that?  

    project 2010

    task is Fixed Duration and not Effort Driven

    I had saved a baseline too.

    Thanks in advance.


    • Edited by jp-pm Thursday, May 10, 2012 2:48 PM left out info
    Thursday, May 10, 2012 2:29 PM

Answers

  • Insert Remaining Work Column and check if its 0 then add to it appropriate hrs. required to complete the task. This should fix the task.

    Sapna S

    • Marked as answer by jp-pm Thursday, May 10, 2012 2:51 PM
    Thursday, May 10, 2012 2:37 PM
    Moderator

All replies

  • Insert Remaining Work Column and check if its 0 then add to it appropriate hrs. required to complete the task. This should fix the task.

    Sapna S

    • Marked as answer by jp-pm Thursday, May 10, 2012 2:51 PM
    Thursday, May 10, 2012 2:37 PM
    Moderator
  • Sapna,

    Perfect!

    Thank you for the answer.  Wow, :-)

    Thank you again....

    :-)

    Thursday, May 10, 2012 2:51 PM
  • You are most Welcome jp-pm, seen you after a long time on the Forum :)

    Sapna S

    Thursday, May 10, 2012 4:51 PM
    Moderator
  • :-)

    Hi Sapna,

    Yes, I've been extremely busy PMing....

    :-)  Hopefully you don't see me this often (it would mean I'm confused) but thank you for acknowledging that

    I haven't been here for awhile....hehehehe.

    Thursday, May 10, 2012 8:26 PM
  • Good to hear from you. You are most Welcome for the feedback.

    Sapna S


    Friday, May 11, 2012 5:28 AM
    Moderator