Portfolio Analysis scoring RRS feed

  • Question

  • Hi all,

    I am trying to understand how the scoring against projects/proposals work. If I select 'No Rating' against a business driver, how does Project Server/Online calculate this? Is it 0 value? If 0 value then how is 'None' treated? If 'None' then what it is the scoring of 'None'?

    Thank you - as always!!!

    Best regards,

    SJ

     

    Monday, October 16, 2017 11:22 AM

All replies

  • Hi SJ,

    I can't test it right now but as far as I remember, if you don't score a project against business drivers, it will have a % of priority equal to 0%.

    Then the selection (or not) depends on the custom field you use for the cost limit or resource role. You could have a 0% priority project still selected if it can be budgeted and if you have enough capacity.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller

    Monday, October 16, 2017 11:47 AM
    Moderator
  • Thank you Guillaume!

    How about 'None'? Is that 0% also? If yes then there is no difference between how the algorithm treats "This proposal doesn't require assessment against this driver (No Rating)" situation vs "This proposal doesn't contribute to this driver at all (None)" situation.

    Thanks in advance...again :-)

    Best regards,

    SJ

    Monday, October 16, 2017 3:34 PM