How to monitor BCWS,BCWP,ACWP value RRS feed

All replies

  • Hi,

    First you have to save a baseline of you project plan and set a status date. Then EV being about costs, you have to ensure that you resources assigned on tasks have a standard rate.


    Hope this helps,


    Guillaume Rouyre, MBA, MCP, MCTS |


    Thursday, September 18, 2014 11:04 AM
    Moderator
  • Hi,

    You would need to take a Baseline of your original project plan and make sure the resources have some rates defined (before taking the baseline). Also you will need to set the Status Date for the project.

    If you use just the %Complete to track your project, without changing dates/resources etc. then your project will be all the time on track (CPI and SPI = 1)

    Some details can be found here: http://www.epmcentral.com/articles/evoverview.php

    Hope this helps

    Paul

    Thursday, September 18, 2014 11:06 AM
  • Thank you.
    I think I saved baseline and assigned rates for resouce.

    But where is Status Date setting ? I could not find that .

    Friday, September 19, 2014 12:53 AM
  • See reference below for setting status date in Project 2007 by going to the project menu then project information:

    http://giabetiu.wordpress.com/2010/04/25/evm-in-microsoft-project-2007/


    Hope this helps,


    Guillaume Rouyre, MBA, MCP, MCTS |

    Friday, September 19, 2014 1:37 AM
    Moderator