none
Near Future Window not shown RRS feed

  • Question

  • Dear Project Server users,

    I have noticed I am not seeing the near Future window in my Task list.
    So I have created a task with a start date set to 10/2/2017 (second of October).

    I expected to see the Near Future window now however I don't.
    Does anyone have any idea why?

    With best regards,
    Petar

    Thursday, September 28, 2017 12:45 PM

All replies

  • PetarB --

    The Planning Windows are controlled by a setting specified by your Project Server administrator.  Ask him to navigate to the PWA Settings page and to click the Task Settings and Display link in the Time and Task Management section of the page.  On the Task Settings and Display page, there is an option named Define Near Future Planning Window.  The value for this option determines what constitutes a Near Future task.  The default setting is 2, which means that the Near Future planning window would show tasks scheduled for next week and the following week.  What value has the administrator entered in this field?  It sounds like he has entered a 0 value in this field.  If so, he needs to change it back to 2.  Hope this helps.


    Dale A. Howard [MVP]

    Thursday, September 28, 2017 1:19 PM
    Moderator
  • Hi Dale,

    Thank you for your answer. 
    Here is the setting i have.
    I think next week should be included with this setting.


    Friday, September 29, 2017 7:48 AM