Progress on Milestones (Project Server 2013 SEM) RRS feed

  • Question

  • Hi,

    How to enter progress on a milestone (Duration = 0) when using the SEM and we have the option : Only allow task updates via Tasks and Timesheets?

    Sunday, May 29, 2016 2:40 PM

Answers

  • Hi,

    Since a milestone has no resource/work and doesn't represent an activity but a deliverable, it is supposed to be 0 or 100%. I just tested and it works well setting the milestone at 100%. The "allow task updates via tasks and timesheets" just block having actual work on assignments, thus it should not occur with milestones.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, MCC |

    • Marked as answer by WLID1966 Monday, May 30, 2016 7:20 AM