none
Units of Work in Dashboard Designer 2010 RRS feed

  • Question

  • Hi,

    How can we know what is the unit used by Dashboard Designer (PerformancePoint) to display the Actual Work Billable calculated in the Timesheet cube ?

    Hours, Person/days ?

    Thanks

    Tuesday, July 19, 2011 12:45 PM

Answers

  • Hi WLID1966,

    All work values in the project server cubes are in hours.

    The units used to display those work values are however defined in the individual reports (e.g. you could divide by 8 to get actual work in days on the report).

    So you should check the report definition to see in what units Actual Work Billable is expressed. But as long the report does not override this, Actual Work will be expressed in hours.

    I hope this helps,
    Hans


    My EPM blog: Projectopolis
    • Marked as answer by WLID1966 Tuesday, July 19, 2011 7:48 PM
    Tuesday, July 19, 2011 7:31 PM
    Moderator