Microsoft Project Format RRS feed

  • Question

  • I have been asked to supply a construction programme in the form of a 'preliminary bar chart and network diagram' showing the earliest and latest date for commencement and completion of tasks. 

    Is there a default view for this? Or is it two different views?

    Wednesday, April 12, 2017 7:37 AM

All replies

  • Hi,

    Basically you would create your project schedule using the Gantt Chart and then you can switch to the network diagram which is also a default view. Note that those views don't give you the earliest and latest dates as you wish, but you can use the slack and critical path which will give you the same information.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller

    Wednesday, April 12, 2017 1:21 PM
    Moderator
  • Hi Guillaume

    Thanks for the info. Are we talking slack or total slack. Presume the latter.

    Regards Brian

    Wednesday, April 26, 2017 8:05 AM